Combined Cycled Thermoelectric Power Plants

In recent decades these power plants have undergone significant growth worldwide. INITEC Energía has actively participated in this evolution, acquiring extensive experience in this field. The facilities within which our company has undertaken its activity add up to total power of close to 9000 MW. This participation covers everything from Property engineering to the “turnkey” provision of facilities, as well as viability studies, execution of reforms and improvements to existing facilities, passing through design phases, detail engineering, management of materials and sub-contracts, supervision of construction, tests, start-up and support for exploitation.

Parnaiba 4 Combined Cycle Power Pant (CCGT)

  • Situation: Brazil
  • Type:
  • Client: UTE Parnaiba Geraçao (MPX)
  • Power: 517 MW (2x1)
  • EPC project on a lump sum “turnkey” basis of a combined cycle power plant on a 2x1 configuration in the Brazilian state of Maranhao. General Electric is the supplier of the gas turbines and the steam turbine.