Award of the Contract "Cogeneration Power Plant in Jorf Lasfar"

     With date July 24th, the OCP (Office Cheriffien des Phosphates) notified us of the official award by signing on its behalf the above-mentioned Contract.
     The project, located in the industrial area of Jorf Lasfar, will last 28 months until the mechanical reception and 31 months until the provisional acceptance, consists of the Engineering, Procurement, Construction and Start-up of a cogeneration related with a sulfuric acid plant with two steam turbines of 60 MW each.
     This award confirms our company as one of the international reference contractors in Morocco, where, although we count with previous references, we have been working for more than eight years and in which we have many hopes in the medium and short term, both in our energy and fertilizer lines of business.
     This cogeneration adds another reference to the already long list of cogenerations that we have executed and continue to execute successfully back from our beginnings.