Initec Energía synchronizes the gas turbine at full load in Navoi project

On September 5, it was the first synchronization of gas turbine generator of Navoi combined cycle plant to Uzbekistan’s power grid. The power generated at the first time ranged from 15 to 24 MW.

On September 10, after commissioning of main equipment and blow down of steam systems, g...

More info

24 / 08 / 2012

The concreting of boilers in Parnaiba project is completed, Brazil

The concreting works of the base of boilers 1 and 2, of the pedestal of the first gas turbine as well as the footings of the electrical building of the Parnaiba project have been successfully completed.

The plant, with a capacity of 500 MW and part of Parnaiba thermoelectric complex is cu...

More info

20 / 07 / 2012

Initec Energía signs the Giza North Project

On last July 17 the signing of the EPC contract for the construction of the BOP mechanical package (Balance of Plant) of the Giza North Combined Cycle Power Plant took place at the headquarters of the Ministry of Energy and Electricity of the Arab Republic of Egypt.

The Plant, located in ...

More info

11 / 04 / 2012

Initec Energía completes successfully the energizing of the combined cycle of Navoi

The energizing process at the Navoi plant was completed successfully on last 11 April.
The plant receives energy from the 220 kV net from another existing plant. This whole process includes the energizing of the new power line of 220 kV, the new substation located inside the plant, the gas...

More info

29 / 03 / 2012

Initec Energía participates in the 2012 Induforum

Initec Energía has participated in the job fair 2012 Induforum, organized by the High School of Industrial Engineers of Universidad Politécnica in Madrid, held on 27 and 28 March.


Induforum is a reference forum for companies at the time of recruiting qualified profes...

More info

Page: 1 2 3 4 5 6 7 8 9